What This Area Is For
Projects is the hub for multi-job installation and project work: one project record holds the plan (Gantt), the jobs engineers carry out, the money (contract value, invoice stages, variations, costs), documents, site safety information and the handover checklist. Engineers keep working jobs in the app exactly as before — the project is the office's view over all of them.
The Projects menu entry only appears when the module is switched on for your organisation (Setup → Project Settings). If it is off, the Projects URL takes you to Project Settings.
What You'll See On The Projects List
- Three views: List (table with a column chooser — your column choices and sort are remembered), Cards, and Timeline (every live project as a bar from start to forecast finish, milestones as diamonds, colour = health).
- Filters: search (number, title, customer, site, ref), status (grouped by stage: pre-award, live, commissioning, complete, closed), health, project manager, type, maintenance (sold / quoted / none), start date range, include closed / archived.
- Tasks and Invoice schedule buttons open the two cross-project pages described below.
- Health chips: On track, At risk (a task is late by more than the threshold in settings, or the forecast finish is past the target), Late (today is past the target), On hold, Complete.
- Columns available: number, title, customer, site, status, health, PM, progress, start, target, forecast, next milestone, jobs done/total, open tasks, overdue tasks, maintenance (Sold / Quoted), customer ref, type, created, and — for users with the view project money permission — contract, invoiced, to invoice, outstanding, PO committed.
- Bulk bar (tick rows): set status, assign PM, archive, export selected to Excel.
- New Project: from scratch, from an accepted quote (copies customer, site, value and refs; links the quote and attaches any job it already produced), or by wrapping an existing job (the job becomes the first job on the project and keeps its number, documents and labour). A plan template can be applied at the same time. In the From scratch form, users who can edit customers get + New next to the Customer picker — it creates the customer (and a first site) without leaving the form and selects them.
Project Tasks
Every task from every live project on one page. Chips along the top switch between Open, Overdue, Due in 7 days, In progress, Not started, Blocked, Complete and All, each showing its count. Filter by owner (assigned to me, unassigned, any office user or engineer), project, project manager, tasks vs milestones, due-date range, and optionally include closed projects. Tick the box on a row to complete (or un-complete) a task — that is the same action as on the project's Tasks tab, so plan dates, auto-complete rules and history behave identically. Click a row to open the project's Tasks tab.
Your Own Tasks
If any open plan task is assigned to you, the page opens on Assigned to me (switch to everyone's with the owner filter or the link under the title). The same number shows everywhere: a red badge on the Projects button in the nav (hover it for "N tasks assigned to you, M overdue"), a Project tasks assigned to you row in the bell's Needs Attention list, and a My Projects tile on the dashboard — open tasks, how many are past their planned finish or due in the next 7 days, the projects you manage (and how many are at risk or late), and with the money permission the stages ready to invoice; every line links to the filtered list. A task counts when it is open (not complete / N/A) on a live project (not archived, not in a closed or cancelled status).
Engineers see the tasks assigned to them too, read-only: a Project Tasks page in the engineers portal (with the open count on its nav button) and, in the app, a My project tasks tile on the home screen that opens the list — project, due date, overdue flag, and an Open job button when the task is linked to one of their jobs. The office still plans and completes tasks; a job-linked task completes itself when the job is completed. Projects are never stored on the phone, so this needs a signal.
Switching the tiles off (Setup → Project Settings → My tasks — where people see them, both on by default, like the HR holiday tile and the app's vehicle tile): "My Projects" tile on the admin dashboard hides the dashboard card; Engineers see tasks assigned to them removes the app tile and the engineers-portal page, so tasks assigned to engineers stay an office-side planning fact. The Projects button count, the bell row and the Project Tasks page are part of the module and stay.
Automations: The Core can react to plan tasks. Triggers under Projects: a project task is assigned to someone (with Assigned to = office user / engineer / both, and whether it was assigned when the task was created), a project task is completed, reopened, marked blocked, and a project milestone is reached. Conditions include the task (title, type, status, priority, due date, days until due, overdue, critical path, auto-complete rule), its owner, the project (number, title, health, manager, phase) and the project's customer and site. Two recipients exist for them: The task owner (the office user and/or engineer the task is assigned to) and The project's manager. The in-app notification's Open link lands on the task in the project. Merge tags: {{title}}, {{project_number}}, {{project_title}}, {{planned_finish}}, {{days_until_due}}, {{owner_name}}, {{phase_title}}, {{customer_name}}, {{site_name}}.
Project Invoice Schedule
For finance: every invoice stage across every live project. Chips show Ready to invoice, Planned, Open, Invoiced · awaiting payment, Paid and All, each with the count and the payable total. Filter by project, customer, PM, trigger type, due-date range and stage amount range. Each row shows stage, trigger, % / amount, retention, payable, status, due date and the linked invoice. Raise on a Ready stage opens the same invoice screen the project's Money tab uses (planned stages can be raised early). Needs the view project money permission; raising needs edit project money.
The Project Page
Header: project number, title, status (click to change), health, type, PM, customer → site breadcrumb, refs, source quote, progress bar and stat chips (start, target, forecast, contract, invoiced, outstanding, PO committed, cost to date). Actions: Edit, New job, New PO, Group chat (when your company uses Messages and you do — see A group chat for the project below), PDF (Project Plan, Order Acknowledgement, Gantt chart, Site Safety sheet), Export (MS Project XML, Excel workbook, tasks CSV, milestones .ics), and a menu with Take baseline, Apply plan template, Recalculate, Archive, Delete.
Edit changes the project's title, type, project manager, lead engineer, refs, Customer and Site, dates, defects period, progress method and description (plus contract value, budget and retention with the money permission). A project created without a customer can be given one here, and a wrong one changed; the Site list shows the chosen customer's sites. Jobs already on the project keep their own customer — the window says so when you change it — while new jobs take the project's customer and site.
Tabs
- Overview — details, dates, retention/defects, plan summary (milestones, open tasks by owner, phases), contacts (link a customer contact or type one — site contact, client PM, principal contractor…), notes, and a Needs attention box (overdue tasks, unscheduled jobs, visits outside the plan, purchase orders past due and not received, plant hire past its expected off-hire date, outstanding invoices, stages ready to invoice, open tickets, and — when your own project fields are on — required fields still empty).
- Plan — the Gantt. Phases, tasks, milestones and summary rows; drag to move or resize, drag between bars to create a dependency (finish-to-start by default; double-click a link to change type FS/SS/FF/SF and lag); double-click a bar to edit. Toolbar: Task / Milestone / Phase, zoom (day, week, month, quarter), Today, Baseline ghost bars, Critical path highlight, Checklist items, Group by engineer, expand/collapse, Shift plan by N days, open the Planner. Jobs appear as bars with the engineers' planner visits drawn inside them; a hatched job bar means it is not yet scheduled on the planner.
- Tasks — the same plan as a table with filters (open / overdue / complete, owner, phase, checklist only). Tick to complete. Select tasks and Create jobs from selected to turn dated tasks into child jobs.
- Jobs — the child jobs with status, engineer, start, planner visits, completion (and price with the money permission). Engineer names everyone assigned to the job, the same as the Planner and the job page show. New job inherits customer, site, tax and currency and is numbered per Project Settings; when your company has job presets, a small arrow beside New job opens From Preset — pick a preset and the New job on this project form opens with it already chosen in its Preset box (you can still change it before you create the job). When departments are switched on, a job made here is sent to a department the same way as any new job (see Jobs). Attach existing job; detach (detaching a job does not clear a hand-made Main job link on it).
- Money (permission-gated) — Contract & variations (original value, approved variations, agreed total, the variations register, and the quotes on the project), Invoicing (the invoice schedule of stages with %, amount, retention, trigger and status, plus the tracker of every invoice raised on the project or its jobs) and Costs (budget vs committed vs actual by category and phase, cost to complete, estimated final cost and margin, budget lines).
- Purchasing — every purchase order and plant hire on the project or on one of its jobs: supplier, title, job, status (✓ when received), due date, hire dates and, with the money permission, value. The badge on the tab counts open POs. New PO (also in the page header) raises a PO already linked to the project; Attach existing PO links one that was raised without it; All in PO list opens the Purchase Orders list filtered to the project. A PO is on the project directly (raised here, from a task, or attached — can be detached here) or via job (its job is on the project — follows the job). On a purchase order's own page a Project panel shows the link with Attach to project, Change project and Remove from project; the Purchase Orders list shows a project chip on the PO number. Needs edit purchases on top of edit projects to add, attach or detach.
- Materials — the project's bill of materials: one line per thing the project needs to buy or pull from stock (materials, plant hire, subcontract packages, other) with quantity, unit, expected cost, supplier, part number, optional stock item, and the phase / task it belongs to. The bill is the plan; it is not an order and not stock. Pull quoted kit adds a line for every quoted material on the project's jobs that the bill does not know yet (never duplicates — and a line you removed stays removed); the same happens automatically when the project is recalculated. Add line opens the editor (picking a stock item fills the part number, cost, unit and supplier). Tick lines for Order selected — a normal purchase order is raised for the quantity not yet on order, at the line's cost, with the supplier preselected when the lines agree; it opens for any changes. Assign to job copies ticked lines onto a child job's materials so the engineers' stock picking covers them (sell = cost; the project's price is the contract). Each line shows ordered / received with a progress bar and links to the POs — worked out from the PO lines that point at it, including POs raised from the job page, so nothing is updated by hand — and a status: Planned, On job, Ordered, Part received, Received. The tab badge counts lines not yet fully received. Budget from bill (money edit permission) sets the Costs tab's materials / plant hire / subcontract budget lines from the bill's cost. Cost columns need the project money permission.
- Documents — a folder explorer. The tree on the left shows the folders set up in Project Settings that apply to this project's type (Survey, Supplier quotes, Drawings, RAMS, Order acknowledgement, Correspondence, Commissioning, O&M / Handover, Photos, Other by default), plus any folder created just for this project (New folder on this project), and Unfiled once a file has no folder. Counts sit beside each folder; a folder flagged required for handover that still holds nothing shows an amber marker and a "Still needed for handover" line above the files. Uploads go straight to secure storage into the folder that is selected (from All, into Unfiled — the drop zone says where). Each file has a ⋯ menu: open, rename, Move to…, Upload new version (older versions fold under the current one), Attach to task…, Link to PO…, show / hide from customer, Show to engineers / Hide from engineers, delete. Tick several files for Move to / Show to engineers / Hide from engineers / Delete together, or drag a file (or the selection) onto a folder in the tree; dropping files from your desktop onto a folder uploads them there. The drop zone has visible to customer and visible to engineers ticks, both set from the folder's defaults. A project's own folder has its own ⋯ menu: rename, the default visibility of new files, New files: visible to engineers by default, Who can see (everyone, or only the office users / departments you pick) and delete (its files go to Unfiled). Photos and documents uploaded on the child jobs are listed underneath, grouped by job and by the job's folder, read-only.
- Show to engineers: a file marked this way (an engineers tag on it) appears on every job of the project for the engineers on that job — in the engineers app under Linked Documents → Project, and on the engineers website job page under Project documents — as a link to the one file, so there is no need to attach a copy to each job. Engineers who can see all jobs get them on any job of the project they open. Only the newest version shows; a deleted file goes. It works on its own — the Linked Documents switch in App Settings is not needed. Nothing is shown to engineers until you tick it (every file starts hidden from them). A folder narrowed with Who can see still narrows: an engineer it does not include does not get its files even if ticked (the tag shows a lock). The office job page's Linked Documents lists the same files under Project (shown to engineers). The customer is not affected — Show to customer is separate.
- Safety — Site Safety Info (nearest A&E, first aider, fire assembly point, working hours, welfare, hazards, access/induction notes, emergency contacts; copy from a previous project at the same site), Project RAMS (attach once — every job on the project gets it, engineers sign in the app as usual) and a sign-off coverage matrix of engineer × RAMS × job. Below them, when your company uses Incidents and/or Audits, an Incidents & Audits card lists the incidents and audits linked to the project (see Incidents and audits about a project below).
- Handover — readiness score built from required certificates (issued vs required), required document folders (their file counts update as soon as you upload, replace, move or delete a file on Documents), open snags and incomplete jobs; practical completion, defects period countdown, retention release date; Build handover pack bundles issued certificate PDFs, signed RAMS and chosen document folders into a ZIP saved to the O&M / Handover folder.
- Tickets — tickets linked to the project (raise a snag from here).
- History — the change log (needs Audit Log (History)).
- Your own tabs — when Your own project fields is switched on (see below), each section you set to show as Its own tab is an extra tab — after History unless you have changed the tab order under Project Settings → Project tabs — with an "n of m" count of its fields that are filled in.
Tabs you do not use can be switched off for every project under Setup → Project Settings → Project tabs: they disappear from every project, nothing is deleted, and Overview is always on. A link to a tab you have switched off opens Overview. On the same card you can drag the tabs into the order you want — your own sections included, before or after the built-in tabs — and every project shows them in that order. Overview always stays first.
Your Own Project Fields
When Your own project fields is switched on in Setup → Project Settings, projects show the sections and fields you designed there (the Project Settings page explains how to design them). It is off by default, and with it off the project page is unchanged.
- Where they show — a section set to Its own tab is an extra tab, after History until you drag it somewhere else under Project Settings → Project tabs. A section set to A card on Overview, A card on Handover or A card on Money shows as a card on that tab. Fields you chose to show in the project header appear as a strip under the header.
- Editing — click a value to edit it. There is no Save button, and a 5-second Undo appears after you change a value.
- Stage trackers — click to move one along; each value shows who changed it and when, in the form "Changed by X on date".
- Required fields — a required field left empty turns red, the tab gets a red dot, and it also appears under Overview → Needs attention as the field's name followed by "not filled in". It never blocks a save.
- Fields read from the plan — a field set to Take it from the plan says "From the plan:" followed by the task it reads from, or "Not on this project's plan — typed here" for a project whose plan does not have it.
- Who can use them — seeing them needs view projects and changing a value needs edit projects. Money fields, and cards on the Money tab, also need the project money permission.
How Tasks Complete Themselves
A task can be linked to a job, purchase order, quote / variation, ticket, certificate type or document folder and given an auto-complete rule. The task completes when the linked thing reaches its done state — the job is completed, the PO is received (or off-hired for plant hire), the quote is accepted, the ticket is closed, a certificate of that type is issued on a child job, or a document lands in the folder. Invoice stages likewise flip to Ready to invoice when their trigger (date, milestone, % complete) is met. The task panel has Create job and Create PO buttons: Create PO raises a purchase order on the project named after the task, links it, sets the rule to "PO received" and opens the PO for the supplier and lines.
Variations
A variation is a quote flagged against the project (Money → New variation quote, or from a quote's Project button). It prices, prints, emails and is accepted exactly like any quote. When the customer accepts, the variations register shows it approved and the agreed total updates. Numbered V01, V02… If a variation quote is deleted, it disappears from the register and from the approved total (the V-number is not reused).
Quotes and maintenance on a project
Money → Quotes on this project has three buttons:
- New quote — a normal quote for the works (tender, main contract, extras), opened in the standard quote editor already linked to the project. Not a variation.
- New variation quote — a change order (see Variations).
- New maintenance quote — a PPM quote for a maintenance agreement sold alongside the install. It opens in the PPM quote editor linked to the project.
Maintenance sold on the Overview shows whether a maintenance agreement was quoted or sold with the project: Quoted while a PPM quote on the project is open, Sold once it is accepted into a PPM contract (with the annual price, visits per year and links to the quote and contract), No if none. It is read from the PPM quote and contract — there is nothing to type in, and maintenance value is not added to the project's agreed total because it is recurring revenue handled by PPM.
Incidents and audits about a project
When your company has the Incidents and/or Audits module switched on (Setup → Incidents Setup, Setup → Audits Setup) and you are allowed to view that module, the project's Safety tab has an Incidents & Audits card below the site safety information, the project RAMS and the sign-off coverage. With neither module on, nothing is drawn. The heading uses your own names for the modules (for example NCRs & Inspections) and names only the ones you can see. If you have switched the Safety tab off under Setup → Project Settings → Project tabs, the card goes with it.
- What it lists: one box per module, headed by the module's name and a count, newest first. Only reports linked to the project itself are listed — an incident linked to one of the project's jobs does not appear here. Each line shows the number (a link that opens the report; Draft until it has one), the template name, its type (an audit's category) and date, and a status chip. A scored audit also shows PASS, FAIL or ADVISORY, and an archived one is tagged archived. The date shown is when the incident occurred or the audit was completed, falling back to the nearest other date the report has (due, submitted or started). A box with nothing in it says None yet. If a box has a very long list, it shows the latest and a See them all link that opens the Incidents (or Audits) list showing only the ones linked to this project.
- Report incident / Start audit: the incidents box has Report incident (for someone who can edit incidents) and the audits box has Start audit (for someone who can edit audits); the wording follows your own module names, for example Start inspection. Each opens the Incidents (or Audits) page with the new-report window already open and the line Will be linked to Project: … — pick the template and press Start, and the new incident or audit is linked to this project.
- Linking one that already exists: open the incident or audit and use its Linked tab — see Incidents and Audits.
A group chat for the project
Group chat in the project header gives the people working on the project one Messages group. It shows only when Messages is switched on for your company and you use Messages yourself.
- The first time it opens Project group chat with a Group name (it starts as "Project" plus the project number and title — change it if you like) and a list of everyone who uses Messages. The people working on the project are listed first and already ticked: the engineers on its jobs and their mates, its lead engineer and its project manager (marked on this project). Tick anyone else, untick anyone who should not be in it, and press Create group. People without Messages are greyed (Messages off). You are always in it.
- Afterwards the same button shows the group's name, its members and the last message, with Open chat (adds you to the group if you were not in it, then opens it on the Messages page), Members (change who is in it, then Save members) and Archive group (press twice to confirm).
- The group appears on everyone's Messages page with a small project icon, and its header has an Open project button back to this page. Engineers and mates chat in it from the app like any other group.
- A project has one group at a time. Archiving or deleting the project archives its group too, and an archived project cannot start a new one.
Common Tasks
A quote with several parts of work (e.g. Mechanic and Tech) that should become a project with a job for each
Do it before the quote is accepted:
- Build the quote with Sections & tasks, one section per part of work, and tick becomes its own job on each section.
- Click the Project button next to the quote number → New project (or Attach an existing project).
- Accept the quote. It makes one job per ticked section (no main job), and all of them land on that project. Everything on the quote must sit in a ticked section — anything outside one is marked Not on a site and stops the quote being sent or accepted.
The quote's Project button is only there until the quote is accepted (it is not shown once the quote has a job). For a quote that is already accepted, use the route below.
Start a project from a quote that is already accepted
- Go to Projects → New Project → From accepted quote and pick the quote. The project copies the customer, site, value and refs, links the quote, and adds the job the quote already made.
- Pick a plan template if you have one — phases, tasks, checklist items, required documents/certificates and invoice stages are stamped out from the start date and Baseline 0 is taken.
- Review the plan; link tasks to jobs and POs as they are raised.
Or use Projects → New Project → Wrap an existing job to make a job the first job on a new project.
On the lifecycle chart a project sits above its quotes and jobs — it is the umbrella the work belongs to, so "project → quote → job" is the expected picture.
Deleting a project takes its jobs, quotes, invoices and purchase orders off it (the records themselves are kept), so they can be added to another project. A deleted project cannot be restored from the recycle bin.
Schedule the work
Create jobs from tasks (Tasks tab) or New job (Jobs tab). Jobs land in the planner's jobs bank; schedule engineers on the Planner as normal — the visits appear inside the job bar on the Gantt. Dragging a job bar on the Gantt moves the plan and offers to shift the planner visits by the same number of days.
Invoice a stage
Money → Invoicing: when a stage reads Ready to invoice, click Raise. The invoice carries one line for the stage amount and, if retention applies, a negative "Less retention held" line; the tracker links to it and shows paid status.
Prepare handover
Handover tab: satisfy the required certificates (engineers issue them on the jobs), upload required documents, close snags, set the practical completion date, then Build handover pack.
Important Options (Project Settings)
Numbering works like job and quote numbering: a prefix (leave blank for plain numbers) and a start from number; the page shows exactly what the next project will be called and updates as you type. New projects continue from the higher of start from and your current highest number. Under Advanced, Share the job number sequence makes a new project take the next job number instead (jobs skip past it) — while that is on, prefix and start from are ignored. Also: how jobs inside a project are numbered (independent, project number + letter, project number / counter), statuses and stage groups, project types, document folders, working calendar (working days, bank holidays, shutdown dates, whether successors may be pulled earlier), health rules, default retention and defects period, snag ticket category, planner colour band, which tabs projects show (Project tabs), your own project fields, plan templates and PDF layouts.
Working calendar — Skip bank holidays (on by default) makes public holidays non-working days when task durations and dependency pushes are worked out. The days are your company's public holidays: the list for your Holiday Region (set in Accounts Settings), plus any days you have added and minus any you have marked We work it under Setup → Pricing → Rules → Public holidays.
Document folders are the folders every project's Documents tab starts with. For each: the name, the default visibility of files dropped in it (internal or customer-visible), New files visible to engineers (off by default — see Show to engineers above), required for handover, the project types it applies to (none ticked = every project) and Who can see it — everyone, or only the office users and departments you pick (a narrowed folder, and the files in it, disappear for everyone else, including from downloads). Reorder by dragging. Deleting a folder sends its files to Unfiled on their projects; nothing is removed from storage. A plan template can carry its own folder set (Plan templates → Folders this template adds) — applying the template adds them to the project as that project's folders.
Common Mistakes
- Expecting engineers to see "projects" in the app — they see the jobs; the project is the office view.
- Editing dates on the Gantt and expecting the planner to change — the Gantt owns the plan; the planner owns visits. Accept the "also shift visits" prompt if you want both moved.
- Setting stage percentages that do not total 100% — the schedule warns but does not block.
- Attaching RAMS on each job individually when the project-level attach does it for every job.
- Typing a start from number while Share the job number sequence is ticked — that option ignores prefix and start from; untick it to use your own project sequence.
- Looking for the Project Plan / Order Acknowledgement layout editor: it is under Setup → PDF Templates → Projects Template, also linked from Project Settings and from a project's PDF menu (Edit … layout).
- Expecting your own project fields on a project while the switch in Project Settings is off — until it is on, the project page is unchanged.
- Looking for a tab that has disappeared — it may have been switched off under Project Settings → Project tabs. A link to a switched-off tab opens Overview.
- Not finding the Incidents & Audits card on a project — it is on the Safety tab, below the safety information, and only shows when the Incidents and/or Audits module is on and you can view it. It lists only the reports linked to the project itself, not ones linked to its jobs.
Related Areas
- Project Settings — module switch, numbering, statuses, folders, calendar, project tabs, your own project fields, templates, PDF layouts.
- Plan templates — reusable plans with tasks, dependencies, jobs to create, invoice stages.
- Planner — scheduling engineers onto the project's jobs.
- Quotes / Invoices / Purchase orders / Tickets — all can be raised against a project.
- Incidents / Audits — the Safety tab lists the ones linked to the project and can start a new one already linked.
- Messages — the project's group chat (Group chat in the header) lives there with the other conversations.